The DPWH seems to tailor the price range objects in a method that makes it simpler for contractors to fulfill necessities for the tasks
MANILA, Philippines – The Senate investigation led by Senator Ping Lacson has uncovered how the price range course of for presidency infrastructure tasks seems to favor contractors.
“Contractor-friendly” was how Lacson characterised it after Senator Sherwin Gatchalian famous how the company appeared to tailor the price range objects in a method that may make it simpler for contractors to fulfill necessities.
Underneath a round from the Division of Finances and Administration (DBM), proposed tasks from the Division of Public Works and Highways (DPWH) are alleged to be “shovel-ready” — full with feasibility research, location coordinates, and secured rights of method, amongst different necessities.
However Gatchalian on Monday, January 19, stated the truth is totally different. “Hinahabol ‘yung pondo, quite than ‘yung pondo ‘yung humahabol sa venture,” he stated. (They chase the funding, as an alternative of the funding following the venture specs.)
“Nagiging lokohan lang ang isina-submit sa DBM (Division of Finances and Administration) para lang magkapondo,” Gatchalian added. (What finally ends up being submitted to the DBM is actually a deception, completed merely to acquire funding.)
Gatchalian flagged how the coordinates for infrastructure tasks indicated within the plan are modified when implementation comes.
Based on former DPWH undersecretary Roberto Bernardo’s earlier testimony, regional and district engineers conspire with authorities contractors to finalize authorities tasks.
Gatchalian confused that tasks ought to be based mostly on endorsements from the Regional Improvement Council, which consists of native authorities officers. By mandate, the RDC is tasked with the coordination, preparation, implementation, monitoring, and analysis of short- and long-term regional improvement plans and funding applications.
Mismatched timeline
Lacson and Gatchalian additionally flagged a mismatch between the DBM’s price range calendar and the RDC’s deliberation course of.
Lacson famous that the DBM’s price range name usually ends round March, whereas RDC deliberations are accomplished solely by August or September, elevating questions on how RDC inputs are totally built-in into the nationwide price range.
DBM Performing Secretary Rolando Toledo stated RDC inputs are thought-about as early as February. From 2025 to 2026, solely about 20% of infrastructure tasks had been endorsed by the RDC, Toledo stated. Sooner or later, Toledo stated that the company goals to make sure that a “majority” of future tasks will carry RDC endorsements.
Former DPWH secretary Manuel Bonoan, nonetheless, stated round 70% of DPWH tasks are endorsed by the RDC.
Transferring ahead, the DPWH stated it can require RDC endorsement for infrastructure tasks.
Bernardo, nonetheless, stated that RDC approval alone doesn’t make tasks corruption-proof. The previous undersecretary, who earlier uncovered corruption schemes throughout the DPWH, stated that many of the tasks implicated within the scheme had additionally been endorsed by the RDC. – Rappler.com